Data Factory Pipeline Copy Data Tasks in Managed VNet

Viewed 118

From the answer given here it can be seen that Copy Data tasks run slowly when using a "Managed Virtual Network" integration runtime. Does anyone know of an alternative or when performance of the copy task within a managed vnet ir is likely to be improved?

1 Answers

As per official documentation you can achieve higher performance by either scale up or scale out the Self-hosted IR.

• You can scale up the self-hosted IR, by increasing the number of concurrent jobs that can run on a node.

Scale up works only if the processor and memory of the node are being less than fully utilized.

• You can scale out the self-hosted IR, by adding more nodes (machines).

when performance of the copy task within a managed vnet ir is likely to be improved?

Regarding above question, you can raise request feature here

Related