I have a list of tasks [Task-A,Task-B,Task-C,Task-D, ...].
One task can be optionally dependent on other tasks.
For example:
A can be dependent on 3 tasks: B, C and D
B can be dependent on 2 tasks: C and E
It's basically a directed acyclic graph and execution of a task should happen only after the dependent tasks are executed.
Now it might happen that at any point of time, there are multiple tasks that are ready for execution. In such a case, we can run them in parallel.
Any idea on how to implement such an execution while having as much parallelism as possible?
class Task{
private String name;
private List<Task> dependentTasks;
public void run(){
// business logic
}
}