In a directed acyclic graph describing a set of tasks to process, i need to find all tasks that can be processed concurrently. The graph has no loops and is quite small (~1000 nodes, ~2000 edges), performance is not a primary concern.
Examples with desired result:
[]is a group. All tasks in a group must be processed before continuing[x & y]meansxandycan be processed concurrently (x and y in parallel)x -> ymeansxandymust be processed sequentially (x before y)
1
a -> [b & c] -> c
2
[a & e] -> b -> c -> [d & f]
3
[ [a -> b] & [e -> f] ] -> [ [c -> d] & g ]
I do not want to actually execute the graph, but rather build a data structure that is as parallel as possible, while maintaining the order. The nomenclature and names of algorithms is not that familiar to me, so i'm having a hard time trying to find similar problems/solutions online.