Hi I have project flow that I need help with. I have multiple projects that start one global project and then some other projects, the problem is the order if I start more than one project simultaneously. For example I have project a and b and I start them at the same time. What I need to happen.
- a->global->c->d
when finished, then
- b->global->c->d
But what happens actually in my project queue:
- a
- b
- global
- global
- c
- c
- d
- d