I have the following code in a JUnit test, which seemed to work last week is failing this week:
Calendar cal = Calendar.getInstance();
cal.set(2011, Calendar.JULY, 12);
cal.set(Calendar.DAY_OF_WEEK, Calendar.FRIDAY); // push the date to 15
System.out.println(cal.get(Calendar.DATE));
As you could probably infer from my comment, since the 12th is a Tuesday, I expect Date to be 15 after setting the DAY_OF_WEEK to Friday. However, the value that is printed is 22, and causes the test to fail.
If I, however change the code as follows, and add an additional call to get:
Calendar cal = Calendar.getInstance();
cal.set(2011, Calendar.JULY, 12);
System.out.println(cal.get(Calendar.DATE));
cal.set(Calendar.DAY_OF_WEEK, Calendar.FRIDAY); // push the date to 15
System.out.println(cal.get(Calendar.DATE));
I get the output that I expect, 12 and 15.
Can someone explain what is going on, and why this test was working last week?