Count work days between two dates

Viewed 428901

How can I calculate the number of work days between two dates in SQL Server?

Monday to Friday and it must be T-SQL.

24 Answers

For workdays, Monday to Friday, you can do it with a single SELECT, like this:

DECLARE @StartDate DATETIME
DECLARE @EndDate DATETIME
SET @StartDate = '2008/10/01'
SET @EndDate = '2008/10/31'


SELECT
   (DATEDIFF(dd, @StartDate, @EndDate) + 1)
  -(DATEDIFF(wk, @StartDate, @EndDate) * 2)
  -(CASE WHEN DATENAME(dw, @StartDate) = 'Sunday' THEN 1 ELSE 0 END)
  -(CASE WHEN DATENAME(dw, @EndDate) = 'Saturday' THEN 1 ELSE 0 END)

If you want to include holidays, you have to work it out a bit...

In Calculating Work Days you can find a good article about this subject, but as you can see it is not that advanced.

--Changing current database to the Master database allows function to be shared by everyone.
USE MASTER
GO
--If the function already exists, drop it.
IF EXISTS
(
    SELECT *
    FROM dbo.SYSOBJECTS
    WHERE ID = OBJECT_ID(N'[dbo].[fn_WorkDays]')
    AND XType IN (N'FN', N'IF', N'TF')
)
DROP FUNCTION [dbo].[fn_WorkDays]
GO
 CREATE FUNCTION dbo.fn_WorkDays
--Presets
--Define the input parameters (OK if reversed by mistake).
(
    @StartDate DATETIME,
    @EndDate   DATETIME = NULL --@EndDate replaced by @StartDate when DEFAULTed
)

--Define the output data type.
RETURNS INT

AS
--Calculate the RETURN of the function.
BEGIN
    --Declare local variables
    --Temporarily holds @EndDate during date reversal.
    DECLARE @Swap DATETIME

    --If the Start Date is null, return a NULL and exit.
    IF @StartDate IS NULL
        RETURN NULL

    --If the End Date is null, populate with Start Date value so will have two dates (required by DATEDIFF below).
     IF @EndDate IS NULL
        SELECT @EndDate = @StartDate

    --Strip the time element from both dates (just to be safe) by converting to whole days and back to a date.
    --Usually faster than CONVERT.
    --0 is a date (01/01/1900 00:00:00.000)
     SELECT @StartDate = DATEADD(dd,DATEDIFF(dd,0,@StartDate), 0),
            @EndDate   = DATEADD(dd,DATEDIFF(dd,0,@EndDate)  , 0)

    --If the inputs are in the wrong order, reverse them.
     IF @StartDate > @EndDate
        SELECT @Swap      = @EndDate,
               @EndDate   = @StartDate,
               @StartDate = @Swap

    --Calculate and return the number of workdays using the input parameters.
    --This is the meat of the function.
    --This is really just one formula with a couple of parts that are listed on separate lines for documentation purposes.
     RETURN (
        SELECT
        --Start with total number of days including weekends
        (DATEDIFF(dd,@StartDate, @EndDate)+1)
        --Subtact 2 days for each full weekend
        -(DATEDIFF(wk,@StartDate, @EndDate)*2)
        --If StartDate is a Sunday, Subtract 1
        -(CASE WHEN DATENAME(dw, @StartDate) = 'Sunday'
            THEN 1
            ELSE 0
        END)
        --If EndDate is a Saturday, Subtract 1
        -(CASE WHEN DATENAME(dw, @EndDate) = 'Saturday'
            THEN 1
            ELSE 0
        END)
        )
    END
GO

If you need to use a custom calendar, you might need to add some checks and some parameters. Hopefully it will provide a good starting point.

All Credit to Bogdan Maxim & Peter Mortensen. This is their post, I just added holidays to the function (This assumes you have a table "tblHolidays" with a datetime field "HolDate".

--Changing current database to the Master database allows function to be shared by everyone.
USE MASTER
GO
--If the function already exists, drop it.
IF EXISTS
(
    SELECT *
    FROM dbo.SYSOBJECTS
    WHERE ID = OBJECT_ID(N'[dbo].[fn_WorkDays]')
    AND XType IN (N'FN', N'IF', N'TF')
)

DROP FUNCTION [dbo].[fn_WorkDays]
GO
 CREATE FUNCTION dbo.fn_WorkDays
--Presets
--Define the input parameters (OK if reversed by mistake).
(
    @StartDate DATETIME,
    @EndDate   DATETIME = NULL --@EndDate replaced by @StartDate when DEFAULTed
)

--Define the output data type.
RETURNS INT

AS
--Calculate the RETURN of the function.
BEGIN
    --Declare local variables
    --Temporarily holds @EndDate during date reversal.
    DECLARE @Swap DATETIME

    --If the Start Date is null, return a NULL and exit.
    IF @StartDate IS NULL
        RETURN NULL

    --If the End Date is null, populate with Start Date value so will have two dates (required by DATEDIFF below).
    IF @EndDate IS NULL
        SELECT @EndDate = @StartDate

    --Strip the time element from both dates (just to be safe) by converting to whole days and back to a date.
    --Usually faster than CONVERT.
    --0 is a date (01/01/1900 00:00:00.000)
    SELECT @StartDate = DATEADD(dd,DATEDIFF(dd,0,@StartDate), 0),
            @EndDate   = DATEADD(dd,DATEDIFF(dd,0,@EndDate)  , 0)

    --If the inputs are in the wrong order, reverse them.
    IF @StartDate > @EndDate
        SELECT @Swap      = @EndDate,
               @EndDate   = @StartDate,
               @StartDate = @Swap

    --Calculate and return the number of workdays using the input parameters.
    --This is the meat of the function.
    --This is really just one formula with a couple of parts that are listed on separate lines for documentation purposes.
    RETURN (
        SELECT
        --Start with total number of days including weekends
        (DATEDIFF(dd,@StartDate, @EndDate)+1)
        --Subtact 2 days for each full weekend
        -(DATEDIFF(wk,@StartDate, @EndDate)*2)
        --If StartDate is a Sunday, Subtract 1
        -(CASE WHEN DATENAME(dw, @StartDate) = 'Sunday'
            THEN 1
            ELSE 0
        END)
        --If EndDate is a Saturday, Subtract 1
        -(CASE WHEN DATENAME(dw, @EndDate) = 'Saturday'
            THEN 1
            ELSE 0
        END)
        --Subtract all holidays
        -(Select Count(*) from [DB04\DB04].[Gateway].[dbo].[tblHolidays]
          where  [HolDate] between @StartDate and @EndDate )
        )
    END  
GO
-- Test Script
/*
declare @EndDate datetime= dateadd(m,2,getdate())
print @EndDate
select  [Master].[dbo].[fn_WorkDays] (getdate(), @EndDate)
*/
 DECLARE @TotalDays INT,@WorkDays INT
 DECLARE @ReducedDayswithEndDate INT
 DECLARE @WeekPart INT
 DECLARE @DatePart INT

 SET @TotalDays= DATEDIFF(day, @StartDate, @EndDate) +1
 SELECT @ReducedDayswithEndDate = CASE DATENAME(weekday, @EndDate)
  WHEN 'Saturday' THEN 1
  WHEN 'Sunday' THEN 2
  ELSE 0 END 
 SET @TotalDays=@TotalDays-@ReducedDayswithEndDate
 SET @WeekPart=@TotalDays/7;
 SET @DatePart=@TotalDays%7;
 SET @WorkDays=(@WeekPart*5)+@DatePart

 RETURN @WorkDays

I know this is an old question but I needed a formula for workdays excluding the start date since I have several items and need the days to accumulate correctly.

None of the non-iterative answers worked for me.

I used a defintion like

Number of times midnight to monday, tuesday, wednesday, thursday and friday is passed

(others might count midnight to saturday instead of monday)

I ended up with this formula

SELECT DATEDIFF(day, @StartDate, @EndDate) /* all midnights passed */
     - DATEDIFF(week, @StartDate, @EndDate) /* remove sunday midnights */
     - DATEDIFF(week, DATEADD(day, 1, @StartDate), DATEADD(day, 1, @EndDate)) /* remove saturday midnights */

None of the functions above work for the same week or deal with holidays. I wrote this:

create FUNCTION [dbo].[ShiftHolidayToWorkday](@date date)
RETURNS date
AS
BEGIN
    IF DATENAME( dw, @Date ) = 'Saturday'
        SET @Date = DATEADD(day, - 1, @Date)

    ELSE IF DATENAME( dw, @Date ) = 'Sunday'
        SET @Date = DATEADD(day, 1, @Date)

    RETURN @date
END
GO

create FUNCTION [dbo].[GetHoliday](@date date)
RETURNS varchar(50)
AS
BEGIN
    declare @s varchar(50)

    SELECT @s = CASE
        WHEN dbo.ShiftHolidayToWorkday(CONVERT(varchar, [Year]  ) + '-01-01') = @date THEN 'New Year'
        WHEN dbo.ShiftHolidayToWorkday(CONVERT(varchar, [Year]+1) + '-01-01') = @date THEN 'New Year'
        WHEN dbo.ShiftHolidayToWorkday(CONVERT(varchar, [Year]  ) + '-07-04') = @date THEN 'Independence Day'
        WHEN dbo.ShiftHolidayToWorkday(CONVERT(varchar, [Year]  ) + '-12-25') = @date THEN 'Christmas Day'
        --WHEN dbo.ShiftHolidayToWorkday(CONVERT(varchar, [Year]) + '-12-31') = @date THEN 'New Years Eve'
        --WHEN dbo.ShiftHolidayToWorkday(CONVERT(varchar, [Year]) + '-11-11') = @date THEN 'Veteran''s Day'

        WHEN [Month] = 1  AND [DayOfMonth] BETWEEN 15 AND 21 AND [DayName] = 'Monday' THEN 'Martin Luther King Day'
        WHEN [Month] = 5  AND [DayOfMonth] >= 25             AND [DayName] = 'Monday' THEN 'Memorial Day'
        WHEN [Month] = 9  AND [DayOfMonth] <= 7              AND [DayName] = 'Monday' THEN 'Labor Day'
        WHEN [Month] = 11 AND [DayOfMonth] BETWEEN 22 AND 28 AND [DayName] = 'Thursday' THEN 'Thanksgiving Day'
        WHEN [Month] = 11 AND [DayOfMonth] BETWEEN 23 AND 29 AND [DayName] = 'Friday' THEN 'Day After Thanksgiving'
        ELSE NULL END
    FROM (
        SELECT
            [Year] = YEAR(@date),
            [Month] = MONTH(@date),
            [DayOfMonth] = DAY(@date),
            [DayName]   = DATENAME(weekday,@date)
    ) c

    RETURN @s
END
GO

create FUNCTION [dbo].GetHolidays(@year int)
RETURNS TABLE 
AS
RETURN (  
    select dt, dbo.GetHoliday(dt) as Holiday
    from (
        select dateadd(day, number, convert(varchar,@year) + '-01-01') dt
        from master..spt_values 
        where type='p' 
        ) d
    where year(dt) = @year and dbo.GetHoliday(dt) is not null
)

create proc UpdateHolidaysTable
as

if not exists(select TABLE_NAME from INFORMATION_SCHEMA.TABLES where TABLE_NAME = 'Holidays')
    create table Holidays(dt date primary key clustered, Holiday varchar(50))

declare @year int
set @year = 1990

while @year < year(GetDate()) + 20
begin
    insert into Holidays(dt, Holiday)
    select a.dt, a.Holiday
    from dbo.GetHolidays(@year) a
        left join Holidays b on b.dt = a.dt
    where b.dt is null

    set @year = @year + 1
end

create FUNCTION [dbo].[GetWorkDays](@StartDate DATE = NULL, @EndDate DATE = NULL)
RETURNS INT 
AS
BEGIN
    IF @StartDate IS NULL OR @EndDate IS NULL
        RETURN  0

    IF @StartDate >= @EndDate 
        RETURN  0

    DECLARE @Days int
    SET @Days = 0

    IF year(@StartDate) * 100 + datepart(week, @StartDate) = year(@EndDate) * 100 + datepart(week, @EndDate) 
        --same week
        select @Days = (DATEDIFF(dd, @StartDate, @EndDate))
      - (CASE WHEN DATENAME(dw, @StartDate) = 'Sunday' THEN 1 ELSE 0 END)
      - (CASE WHEN DATENAME(dw, @EndDate) = 'Saturday' THEN 1 ELSE 0 END)
      - (select count(*) from Holidays where dt between @StartDate and @EndDate)
    ELSE
        --diff weeks
        select @Days = (DATEDIFF(dd, @StartDate, @EndDate) + 1)
      - (DATEDIFF(wk, @StartDate, @EndDate) * 2)
      - (CASE WHEN DATENAME(dw, @StartDate) = 'Sunday' THEN 1 ELSE 0 END)
      - (CASE WHEN DATENAME(dw, @EndDate) = 'Saturday' THEN 1 ELSE 0 END)
      - (select count(*) from Holidays where dt between @StartDate and @EndDate)
 
    RETURN  @Days
END
DECLARE @StartDate datetime,@EndDate datetime

select @StartDate='3/2/2010', @EndDate='3/7/2010'

DECLARE @TotalDays INT,@WorkDays INT

DECLARE @ReducedDayswithEndDate INT

DECLARE @WeekPart INT

DECLARE @DatePart INT

SET @TotalDays= DATEDIFF(day, @StartDate, @EndDate) +1

SELECT @ReducedDayswithEndDate = CASE DATENAME(weekday, @EndDate)
    WHEN 'Saturday' THEN 1
    WHEN 'Sunday' THEN 2
    ELSE 0 END

SET @TotalDays=@TotalDays-@ReducedDayswithEndDate

SET @WeekPart=@TotalDays/7;

SET @DatePart=@TotalDays%7;

SET @WorkDays=(@WeekPart*5)+@DatePart

SELECT @WorkDays

As with DATEDIFF, I do not consider the end date to be part of the interval. The number of (for example) Sundays between @StartDate and @EndDate is the number of Sundays between an "initial" Monday and the @EndDate minus the number of Sundays between this "initial" Monday and the @StartDate. Knowing this, we can calculate the number of workdays as follows:

DECLARE @StartDate DATETIME
DECLARE @EndDate DATETIME
SET @StartDate = '2018/01/01'
SET @EndDate = '2019/01/01'

SELECT DATEDIFF(Day, @StartDate, @EndDate) -- Total Days
  - (DATEDIFF(Day, 0, @EndDate)/7 - DATEDIFF(Day, 0, @StartDate)/7) -- Sundays
  - (DATEDIFF(Day, -1, @EndDate)/7 - DATEDIFF(Day, -1, @StartDate)/7) -- Saturdays

Best regards!

I borrowed some ideas from others to create my solution. I use inline code to ignore weekends and U.S. federal holidays. In my environment, EndDate may be null, but it will never precede StartDate.

CREATE FUNCTION dbo.ufn_CalculateBusinessDays(
@StartDate DATE,
@EndDate DATE = NULL)

RETURNS INT
AS

BEGIN
DECLARE @TotalBusinessDays INT = 0;
DECLARE @TestDate DATE = @StartDate;


IF @EndDate IS NULL
    RETURN NULL;

WHILE @TestDate < @EndDate
BEGIN
    DECLARE @Month INT = DATEPART(MM, @TestDate);
    DECLARE @Day INT = DATEPART(DD, @TestDate);
    DECLARE @DayOfWeek INT = DATEPART(WEEKDAY, @TestDate) - 1; --Monday = 1, Tuesday = 2, etc.
    DECLARE @DayOccurrence INT = (@Day - 1) / 7 + 1; --Nth day of month (3rd Monday, for example)

    --Increment business day counter if not a weekend or holiday
    SELECT @TotalBusinessDays += (
        SELECT CASE
            --Saturday OR Sunday
            WHEN @DayOfWeek IN (6,7) THEN 0
            --New Year's Day
            WHEN @Month = 1 AND @Day = 1 THEN 0
            --MLK Jr. Day
            WHEN @Month = 1 AND @DayOfWeek = 1 AND @DayOccurrence = 3 THEN 0
            --G. Washington's Birthday
            WHEN @Month = 2 AND @DayOfWeek = 1 AND @DayOccurrence = 3 THEN 0
            --Memorial Day
            WHEN @Month = 5 AND @DayOfWeek = 1 AND @Day BETWEEN 25 AND 31 THEN 0
            --Independence Day
            WHEN @Month = 7 AND @Day = 4 THEN 0
            --Labor Day
            WHEN @Month = 9 AND @DayOfWeek = 1 AND @DayOccurrence = 1 THEN 0
            --Columbus Day
            WHEN @Month = 10 AND @DayOfWeek = 1 AND @DayOccurrence = 2 THEN 0
            --Veterans Day
            WHEN @Month = 11 AND @Day = 11 THEN 0
            --Thanksgiving
            WHEN @Month = 11 AND @DayOfWeek = 4 AND @DayOccurrence = 4 THEN 0
            --Christmas
            WHEN @Month = 12 AND @Day = 25 THEN 0
            ELSE 1
            END AS Result);

    SET @TestDate = DATEADD(dd, 1, @TestDate);
END

RETURN @TotalBusinessDays;
END